No.
|
Recommendation
|
Actions
|
Comments
|
Target Completion
|
Revised Completion
|
Actual Completion
|
1.
|
Confirmation that all staff are working to the same policies and procedures.
Our findings tell us there are some inconsistencies. Are they audited; Scrutiny would like to see those results. How are managers making sure contact points are being met.
|
- R&M Manager to meet with Managers & key staff to go through the current process for recording & reporting D&M cases.
|
Agreed recommendation.
NB. There is no Policy for Damp and mould.
|
June 24
|
August 2024
Property team – reviewed process - revised reporting sheet
Hub Team – due to their workloads and staff leaving were unable to commit in June to review. Will review in August.
Housing/supported teams aware of process and use Total Mobile form.
Further review will be required once new CM process is in place.
|
|
- Internal independent Audit of D&M process
|
TIAA will be conducting an audit of the D&M process. Scope for the audit is due for review and discussion in August 24 with the review in Sept 24.
|
Sept’ 24
|
|
|
- Implement the new D&M process.
|
New process map is being reviewed against the Ombudsman guidance to ensure it all correlates with the actions and timescales.
Capital time is scheduled for July 24 to build and implement the required system changes.
|
August 24
|
September 24
|
|
- Communication and training roll out on the new process and new ways for recording, monitoring, and reporting of D&M to key staff working on D&M cases.
|
A comm’s plan will be produced which will include updates to the new process, a training programme for staff working directly with D&M referrals and available guides for new starters.
|
August 24
|
Sept 24
Update
System was built in test at end of July 24. Property, Hub teams tested in early August. Able to be progressed to live pending officer time to update documents, train teams, update process document.
|
|
- Staff Brief item on the new process for D&M following go live.
|
This will be included in the staff brief for October for all staff to be updated on how the new process works, where & how to record, how cases will be monitored through to completion.
|
October 24
|
|
|
2.
|
Where vulnerable persons are involved housing workers should be advised of the situation
Findings indicate that although Westward try to make appointments, some customers need extra support to enable these to take place
|
- Where flag indicates a potential vulnerability within the household, the Housing Workers and key scheme staff will be made aware of booked D&M works.
|
Agreed Recommendation – We will explore how best to build this into the new process.
NB:
For clarification – to schemes where there are site based staff
|
August 24
|
|
|
- Key site-based staff will be made aware of D&M cases where continuous monitoring and assistance may be required so long term support can be provided.
|
A review of the D&M register will be undertaken to review those where vulnerabilities have been identified and ensure the on-site staff are aware of any ongoing works along with any feedback from already completed works to see if a long-term plan needs to be put in place for on-going support.
|
June 24
|
September 24
Update:
This is a large piece of work due to the volume of cases – need to identify resource required to undertake this task.
|
|
3.
|
Staff to ask about any health conditions at first point of contact.
This will ensure that all vulnerable persons are identified, and appropriate follow up action taken.
|
- Reaffirm back to the staff that health conditions need to be established from the outset to ensure correct priority is given to the case.
|
Agreed recommendation
|
June 24
|
July 24
|
July 24
Sheet revised to include capture of health concerns. Hub to be reminded as part of review of process.
|
- New process will include checking on vulnerability and health status.
|
|
August 24
Sheet to be revised to include Vulnerability check.
|
|
|
4.
|
Printed ‘How to guide’ to give to customers without internet access (surveyor)
To provide information on appropriate safe products to use. This can also be printed off by the hub when reports first come in and posted to customer (or email)
|
- Review a leaflet style booklet or postcard with top tips guides that can be given to customers.
|
Recommendation agreed in principle – design options and quotes will be obtained to explore the cost to provide this service for those customers without access to the internet.
|
October 24
|
|
|
- Product recommendations to be explored.
|
Product recommendations will be discussed with the H&S manager to review the requirements under COSHH (Control of Substances Hazardous to Health Regulations).
|
June 24
|
August 24
|
|
- Review the letters within the new process to see what additional information can be included for top tips and guides.
|
This will need to form part of the implementation of the new process and go live planning.
|
August 24
|
September 24
|
|
- Use of Customer newsletter such as Moor to Sea for information sharing for D&M top tips and guidance.
|
Continue to include articles within each edition of Moor to Sea.
|
Autumn Edition 2024
|
|
|
5.
|
Look at damp and mould issue, not in isolation
Not all issues relate to the property itself, could be neighbouring property
|
- Ensure all technical staff are reviewing the potential that there may be defects occurring in neighbouring properties.
|
Agreed recommendation – Technical Surveyors should already be reviewing neighbouring properties to explore the possibilities that they are either the source or contributing towards any signs of D&M in within dwellings.
Build this into the process for inspecting properties with reported damp and mould.
|
June 24
Currently Part of service delivery
|
|
June 24
Currently Part of service delivery
|
- Create a power BI tool to compare archetypes of properties using build data to review for known defects or possible likelihood of suffering from D&M.
|
This will need to follow the implementation and go live for the new D&M process.
|
Nov’ 24
|
|
|
6.
|
Ensure that information and links on website, and those available to staff are up to date and contain most recent information
Recent experience of scrutiny member, sent out of date link.
|
- Conduct a review of the links used within the various strands of customer communication to ensure links are live.
|
A review was carried out and it would appear there was the potential that some links had not worked correctly during the upgrade of the website content.
This will be continually monitored when new links are sent and upgrade works takes place to website content.
|
April 24.
|
|
April 24
|
7.
|
An individual plan for each customer.
Not only does it provide peace of mind for the householder it’s also useful for Westward to monitor how effective cleaning is and how long it takes for issues to reappear.
|
- Review the outcome of Awaabs Law and ensure all customer related actions and timescales are embedded into the new process.
|
This is under review with no date yet confirmed for feedback from the consultation.
|
Awaiting timescales.
|
|
|